Work in progress – February 2019
Update 5.03.2019
The month of February started badly for the lake’s sewage system. As we know, after heavy rains the (more…)
Update 5.03.2019
The month of February started badly for the lake’s sewage system. As we know, after heavy rains the (more…)
Update 25.01.2019
Although the sewage restoration works are almost complete, in the last few weeks there have been various malfunctions and sewage (more…)
According to the latest updates received from COBALB management, the restoration work on the pumping stations of the sewage canal (more…)
Update 7.11.18
A few days after our last update on repair work to the sewerage ring, an inspection of some of the (more…)
Update 29.08.18
In the last days of August, work on Station SS9 in the Grancaro area finished: the new transformer and the new electricity panel (more…)
Update 19.07.18
The restoration work on the circumlacual collector managed by COBALB is nearing completion, even though it was slowed down (more…)
Update 18.06.18
The work of restoring the ring channel collector managed by COBALB continues. Restoration of the mechanical-hydraulic lifting (more…)
Update 5.05.18
The work to restore the lake’s waste water collector is proceeding. The works, which in this first phase address the (more…)
Update 14.04.18
A few days ago the storage tanks in the sewage treatment plant containing a large amount of sewage sludge (about 7,000 cubic meters, (more…)