Work in progress

Work in progress – February 2019

Update 5.03.2019
The month of February started badly for the lake’s sewage system. As we know, after heavy rains the (more…)

Work in progress – January 2019

Update 25.01.2019
Although the sewage restoration works are almost complete, in the last few weeks there have been various malfunctions and sewage (more…)

Work in progress – December 2018

According to the latest updates received from COBALB management, the restoration work on the pumping stations of the sewage canal (more…)

Work in progress – November 2018

Update 7.11.18
A few days after our last update on repair work to the sewerage ring, an inspection of some of the (more…)

Work in progress – August 2018

Update 29.08.18
In the last days of August, work on Station SS9 in the Grancaro area finished: the new transformer and the new electricity panel (more…)

Work in progress – July 2018

Update 19.07.18
The restoration work on the circumlacual collector managed by COBALB is nearing completion, even though it was slowed down (more…)

Work in progress – June 2018

Update 18.06.18
The work of restoring the ring channel collector managed by COBALB continues. Restoration of the mechanical-hydraulic lifting (more…)

Work in progress – May 2018

Update 5.05.18
The work to restore the lake’s waste water collector is proceeding. The works, which in this first phase address the (more…)

Work in progress – April 2018

Update 14.04.18
A few days ago the storage tanks in the  sewage treatment plant containing a large amount of sewage sludge (about 7,000 cubic meters, (more…)