Work in progress – March 2018

Update 26th March 2018

This article on the restoration work of the sewage system managed by COBALB has been updated and corrected on the basis of information kindly
provided by the Lazio Region.

The current status is as follows:

  • The work on the annular ring began on 20th March 2018 and, barring unforeseen events, should be completed before the summer season.
  • Work on the sewage treatment plant will start in a few weeks, the priority being work on the annular ring which is, in some respects, technically preliminary to work on the plant.
  • The state of progress is regularly reported to the Ministry for the Environment and for the Protection of Land and Sea, which passes this on to the European Community.

We will keep you informed about progress.